Regulation (EU) 2023/1230 becomes mandatory on 20 January 2027. This article walks through the key transition dates and what each milestone means for machinery manufacturers.

Machinery Regulation 2023/1230: The Transition Timeline

Regulation (EU) 2023/1230 does not apply overnight. The move from Directive 2006/42/EC to the new Machinery Regulation follows a structured timeline with several key milestones. Understanding these dates is essential for your compliance planning — they determine whether you must comply today, whether you have a choice, and when there is no longer any option.

This article maps the transition from adoption through full application, so you know exactly what you need to do and when. If your machinery is currently compliant with Directive 2006/42/EC, this timeline tells you when and how to move to 2023/1230.

The timeline at a glance

Date Event What it means for you
14 June 2023 Regulation adopted The regulation is formally approved by the EU legislature
29 June 2023 Published in Official Journal The regulation text enters the public record
19 July 2023 Entry into force The regulation becomes law across all EU member states
20 January 2024 Notified body requirements apply New notified bodies must meet 2023/1230 standards from this date
20 January 2027 Full application All machinery placed on the market must comply with 2023/1230

Adoption: 14 June 2023

On 14 June 2023, the European Parliament and Council formally adopted Regulation (EU) 2023/1230, replacing Directive 2006/42/EC. This is the most significant overhaul of EU machinery safety law in decades. The regulation is approved but not yet binding until publication. It signals that preparation should begin.

Publication: 29 June 2023

The full text of Regulation (EU) 2023/1230 was published in the Official Journal of the European Union as OJ L 165, 29 June 2023. This is the moment the regulation becomes binding legal text.

From this date forward, every EU member state, notified body, conformity assessment body, and machinery manufacturer can access the official, definitive text. Industry publications, trade associations, and regulatory bodies issue guidance based on this published text. Formal compliance planning should begin now.

The publication date also determines the trigger for "entry into force" — which occurs twenty days after publication in the Official Journal.

Entry into force: 19 July 2023

Regulation (EU) 2023/1230 entered into force on 19 July 2023 (the twentieth day after publication). It is now legally binding across all EU member states.

However, entry into force does not mean immediate application. During the transition (July 2023 – January 2027), both regulations coexist. You can choose to comply with 2023/1230 immediately, but are not required to. If machinery is placed on the market before 20 January 2027 under Directive 2006/42/EC, the old directive's requirements apply.

This coexistence period gives manufacturers time to update documentation, revise templates, and implement new cybersecurity controls.

Notified body requirements: 20 January 2024

On 20 January 2024, the requirements for notified bodies under Regulation (EU) 2023/1230 applied.

A notified body is a third-party conformity assessment organization (TÜV Rheinland, BSI, Dekra, etc.) that carries out conformity assessment where the Regulation requires third-party involvement.

From 20 January 2024:

  • Notified bodies must be accredited to 2023/1230 standards
  • Existing bodies had to update accreditation or stop accepting new work
  • Machinery already in assessment before this date could finish under 2006/42/EC

For manufacturers: if your machinery requires notified body certification, the body must issue certificates under 2023/1230 procedures from this date forward. Verify your chosen body is accredited under 2023/1230.

Full application: 20 January 2027

On 20 January 2027, Regulation (EU) 2023/1230 becomes fully applicable to all machinery placed on the EU market or put into service. This is the hard deadline — the point at which the old directive no longer applies to any new machinery.

From this date forward:

  • You cannot issue new machinery under Directive 2006/42/EC
  • All machinery must comply with the essential health and safety requirements defined in Annex III of 2023/1230
  • All technical documentation must follow the structure and content requirements defined in Annex IV (Part A for machinery, Part B for partly completed machinery)
  • All Declarations of Conformity must use the template and mandatory content defined in Annex V
  • All notified bodies must operate under 2023/1230 accreditation requirements (if not already done)
  • Machinery placed on the market on or after 20 January 2027 will be audited, inspected, and enforced against 2023/1230 standards by market surveillance authorities

There is no grace period. There is no "we manufactured it under the old directive so it is exempt." The application date is a hard, universal cutover.

What "placed on the market" means in practice

Regulation (EU) 2023/1230 applies to machinery "placed on the market or put into service" from 20 January 2027.

"Placed on the market" means the machinery first becomes available to an end user in the EU — typically shipment date. "Put into service" means first operation by the intended user.

The critical rule: if you manufacture before 20 January 2027 but ship after that date, the regulation that applied on shipment date governs your compliance. In other words:

  • Machinery shipped before 20 January 2027 complies with Directive 2006/42/EC
  • Machinery shipped on or after 20 January 2027 must comply with 2023/1230, regardless of manufacture date

For long-lead-time machinery (6–12 month builds), this creates urgency. You must transition compliance documentation now. Waiting until late 2026 risks shipping non-compliant machinery.

Stock-in-market scenarios

If you distribute machinery through retailers or resellers, the "placed on the market" date applies to each sale. A machine in distributor stock on 20 January 2027 that ships in February 2027 must comply with 2023/1230. Coordinate inventory reduction before the application date to avoid stranded stock.

What you should do now

The transition period (July 2023 – January 2027) allows time to prepare. Start with these actions:

  1. Audit your technical documentation against Annex IV Part A of 2023/1230. Identify gaps and outdated procedures.
  2. Review your Declaration of Conformity template against Annex V. Verify all mandatory content sections are present.
  3. Check notified body requirements. If your machinery requires third-party assessment, start vetting bodies accredited under 2023/1230 now.
  4. Review essential requirements (Annex III). Identify new hazards and new requirements, particularly cybersecurity in Section 1.1.9.
  5. Plan for cybersecurity. If your machinery has networked interfaces or remote operation, Section 1.1.9 mandates new cybersecurity measures.
  6. Set internal milestones. Schedule documentation updates, testing, and final review before 20 January 2027.

Common misconception: the grace period

A frequent mistake: "We can sell under the old directive until 20 January 2027, so we do not need to change anything until late 2026."

This is only true if machinery ships before 20 January 2027. Stock shipping after that date must comply with 2023/1230. Market surveillance authorities will audit for 2023/1230 compliance immediately after the application date. If your machinery has a 4–6 month lead time, begin compliance audits in mid-2026.

Key regulatory references

  • Regulation (EU) 2023/1230 — Article 54 (application date and transition provisions)
  • Official Journal L 165, 29 June 2023 — Publication reference
  • Annex III — Essential health and safety requirements
  • Annex IV, Part A — Technical documentation for machinery
  • Annex IV, Part B — Technical documentation for partly completed machinery
  • Annex V — Declaration of Conformity template and mandatory content

Next steps

This completes our four-part series on Regulation (EU) 2023/1230:

  1. Article 1: The big picture — what is changing and why
  2. Article 2: The Declaration of Conformity — Annex V, mandatory content
  3. Article 3: Technical documentation — Annex IV, the 14 required components
  4. Article 4: The transition timeline — dates, milestones, and action items (this article)

If you have not yet started your compliance transition, begin with Article 1 for context, then work through Articles 2–4 in order. Your immediate next step is to schedule an internal audit of your current technical documentation and DoC template against the new requirements, and establish a project timeline for updates before 20 January 2027.


This article references Regulation (EU) 2023/1230 of the European Parliament and of the Council of 14 June 2023. Full application: 20 January 2027. For the official text, see EUR-Lex. This content is informational and does not constitute legal advice. Consult your Notified Body or regulatory advisor for guidance specific to your products.


Claims Checklist

Claim Source (Article/Annex) Verified
Regulation adopted on 14 June 2023 Title of the Regulation Yes
Published in Official Journal L 165, 29 June 2023 regulatory-facts.md, verified against EU-OSHA and TÜV Rheinland (28 Jul 2026) Yes
Entry into force 19 July 2023 (twentieth day after publication) Art. 54, first paragraph Yes
Notified body requirements apply from 20 January 2024 Art. 54 Yes
Full application date is 20 January 2027 Art. 54, second paragraph Yes
Machinery placed on market from 20 January 2027 must comply with 2023/1230 Art. 54 Yes
Replaces Directive 2006/42/EC regulatory-facts.md, verified 28 Jul 2026 Yes
Declaration of Conformity format is set out in Annex V Annex V Yes
Essential health and safety requirements are in Annex III Annex III Yes
Cybersecurity requirement in Section 1.1.9 of Annex III (not Annex IV) Annex III, Section 1.1.9 Yes